Piles above the ground - Vroom Funderingstechnieken
Img 07
December 18, 2014

Piles above the ground

On elementary school De Sluis’s playground, we have realized four light towers. After insertion, the lowest pile segment was brought into a vertical position and subsequently poured with concrete. Afterwards, the pile was realized by welling the segment parts on top of it.
Default foto 2

The execution was carried out with the Vermeer 1800 rig, one of our smallest engines. This mini rig is equipped with an automated piling system and in theory, unlimited pile lengths can be realized as the foundation piles can be inserted as segment parts.